Please Rotate Your Device.
[Portrait Mode]
About
Parking arrangement
360 Panorama
FAQ
Contact
Timeline
☰
×
About
Parking Arrangement
360 Panorama
FAQ
Contact
Timeline
DICKSON VILLAGE PROJECT TIMELINE TO COMPLETION
The overall development timeframe will be from May 2021 until September 2023. Scroll down to see approximate timeframes for development activities and process photos.
2021
Previous
Next
May 2021
Temporary construction parking , enter from Rosevear Place.
June 2021
McDonalds Dickson driveway widening and carpark works to allow for continued access during construction of Dickson Village
Previous
Next
Previous
Next
July 2021
Car park closing 26 July 2021
August 2021
Trees being relocated
Previous
Next
Previous
Next
September 2021
Construction underway
October 2021
Ongoing bulk earthworks
Previous
Next
Previous
Next
November 2021
Ongoing bulk earthworks
Commencement of Basement 1 Shotcrete
External Services Works
Completion of HV underground relocation
December 2021
Completion of bored piers & capping beam
Ongoing bulk earthworks
Ongoing Basement 1 & 2 Shotcrete
Ongoing external Services Works
Commencement of pad footings
Previous
Next
Previous
Next
January 2022
Ongoing bulk earthworks
Ongoing Basement 1 & 2 Shotcrete
Ongoing External Services Works (Nearing Completion)
Installation of Crane base
Commencement of Hydraulic & Electrical Works
February 2022
Ongoing bulk earthworks (98% complete)
Ongoing Basement 1 & 2 shotcrete (95% complete)
Ongoing Hydraulic & Electrical Works
Basement 2 slab 50% complete
Commencement of Basement 1 slab formwork
Installation and commissioning of Tower Crane 1
Installation of Concrete Tower Pump base
Previous
Next
Previous
Next
March 2022
Bulk Excavation works complete
Basement 1 & 2 shotcrete 98% complete
Ongoing Hydraulic & Electrical works
Basement 2 Slab 70% complete
Basement 1 Slab 45% complete
Tower Crane 1 & 2 installed and operational
Concrete Tower Pump installed and operational
April 2022
Bulk excavation & site retention completed
Earthmat completed
Slab on Ground completed
Basement Precast completed
Basement 1 Suspended Slab 80% completed
First Ground Floor Suspended Slab scheduled for early May
Previous
Next
Previous
Next
May 2022
Slab on Ground Complete
Basement 2 Slab Complete
Basement 1 Slab Complete
Basement Precast Complete
70% B2-GF Stairs & Ramps Complete
55% Ground Floor Slab Complete
-->
June 2022
Coming Soon
July 2022
Coming Soon
August 2022
Coming Soon
September 2022
Coming Soon
October 2022
Coming Soon
November 2022
Coming Soon
December 2022
Coming Soon
January 2023
Coming Soon
February 2023
Coming Soon
March 2023
Coming Soon
April 2023
Coming Soon
May 2023
Coming Soon
June 2023
Coming Soon
July 2023
Coming Soon
August 2023
Coming Soon
September 2023
Coming Soon