DICKSON VILLAGE PROJECT TIMELINE TO COMPLETION

The overall development timeframe will be from May 2021 until September 2023. Scroll down to see approximate timeframes for development activities and process photos.

2021

May 2021
  • Temporary construction parking , enter from Rosevear Place.
June 2021
  • McDonalds Dickson driveway widening and carpark works to allow for continued access during construction of Dickson Village
July 2021
  • Car park closing 26 July 2021
August 2021
  • Trees being relocated
September 2021
  • Construction underway
October 2021
  • Ongoing bulk earthworks
November 2021
  • Ongoing bulk earthworks
  • Commencement of Basement 1 Shotcrete
  • External Services Works
  • Completion of HV underground relocation
December 2021
  • Completion of bored piers & capping beam
  • Ongoing bulk earthworks
  • Ongoing Basement 1 & 2 Shotcrete
  • Ongoing external Services Works
  • Commencement of pad footings
January 2022
  • Ongoing bulk earthworks
  • Ongoing Basement 1 & 2 Shotcrete
  • Ongoing External Services Works (Nearing Completion)
  • Installation of Crane base
  • Commencement of Hydraulic & Electrical Works
February 2022
  • Ongoing bulk earthworks (98% complete)
  • Ongoing Basement 1 & 2 shotcrete (95% complete)
  • Ongoing Hydraulic & Electrical Works
  • Basement 2 slab 50% complete
  • Commencement of Basement 1 slab formwork
  • Installation and commissioning of Tower Crane 1
  • Installation of Concrete Tower Pump base
March 2022
  • Bulk Excavation works complete
  • Basement 1 & 2 shotcrete 98% complete
  • Ongoing Hydraulic & Electrical works
  • Basement 2 Slab 70% complete
  • Basement 1 Slab 45% complete
  • Tower Crane 1 & 2 installed and operational
  • Concrete Tower Pump installed and operational
April 2022
  • Bulk excavation & site retention completed
  • Earthmat completed
  • Slab on Ground completed
  • Basement Precast completed
  • Basement 1 Suspended Slab 80% completed
  • First Ground Floor Suspended Slab scheduled for early May
May 2022
  • Slab on Ground Complete
  • Basement 2 Slab Complete
  • Basement 1 Slab Complete
  • Basement Precast Complete
  • 70% B2-GF Stairs & Ramps Complete
  • 55% Ground Floor Slab Complete
-->
June 2022
user-image
user-image
July 2022
August 2022
user-image
user-image
September 2022
October 2022
user-image
user-image
November 2022
December 2022
user-image
user-image
January 2023
February 2023
user-image
user-image
March 2023
April 2023
user-image
user-image
May 2023
June 2023
user-image
user-image
July 2023
August 2023
user-image
user-image
September 2023