DICKSON VILLAGE PROJECT TIMELINE TO COMPLETION

The overall development timeframe will be from May 2021 until September 2023. Scroll down to see approximate timeframes for development activities and process photos.

2021

May 2021
  • Temporary construction parking , enter from Rosevear Place.
June 2021
  • McDonalds Dickson driveway widening and carpark works to allow for continued access during construction of Dickson Village
July 2021
  • Car park closing 26 July 2021
August 2021
  • Trees being relocated
September 2021
  • Construction underway
October 2021
  • Ongoing bulk earthworks
user-image
November 2021
December 2021
user-image
user-image
January 2022
February 2022
user-image
user-image
March 2022
April 2022
user-image
user-image
May 2022
June 2022
user-image
user-image
July 2022
August 2022
user-image
user-image
September 2022
October 2022
user-image
user-image
November 2022
December 2022
user-image
user-image
January 2023
February 2023
user-image
user-image
March 2023
April 2023
user-image
user-image
May 2023
June 2023
user-image
user-image
July 2023
August 2023
user-image
user-image
September 2023